Scheduled reports

I have a basic question regarding Scheduled reports. How does it work?

I have created a very simple report and I want this report to be sent to myself daily at 12:00.
In Suite, Reports/Scheduled reports, the status is Active and the report is scheduled Daily at 12:00.
The email is setup to myself, and I know that it works (I have tested it).
In Admin/Scheduler, I have set up the Job, “Run scheduled reports”, and the intervall is set Every 1 minute Every Day. (Just during my test.)

But no report is sent to me, and I can see in the “history” that no report has ben run because the field “Last run” is empty.

What is wrong?

In the Job Log subpanel for Scheduler (Run scheduled reports), what does that say?

Now the reports are distributed. We had forgot the setup in crontab file… Thank you!

But I still have one question related to this and it is the time.
In my profile I use the timezone Europe/Stockholm (GMT+2:00), and we have setup the same timezone for the system. But there seems to be something else that we need to change, because if I schedule a report to be run at 16.00, it will not run until 18.00.

For example: The last run for a scheduled report say “Last run: 2015-04-22 16:00:01”, but it was actually run at 18:00 and I received the report at 18:00.

What date do we have to change so the report is run at the time we expect?

Hi,

How you set up the crontab file?

Thanks!
Liz