In the Suite CRM project module, when we assign the number of days for a task to setup the Gantt Chart. It doesn’t take into account the weekends.
What option can be deployed to enables the weekends also to be considered as working days.
For instance in the above image (Hypothetical example)
When I consider 6 days duration - the task finishes on 18 march (as its doesn’t consider Saturday and sunday as working days). whereas it should have been completed on 16 March
Please comment